WRITE for ATol ADVERTISE MEDIA KIT GET ATol BY EMAIL ABOUT ATol CONTACT US
Asia Time Online - Daily News
              Click Here
Asia Times Chinese
AT Chinese



    South Asia
     Dec 7, 2006
Page 2 of 2
India's reform pains

By Kunal Kumar Kundu

irrigation, road works, railways and power, is mind-boggling. According to some estimates, as much as Rs1 trillion (about US$21 billion) may be stuck in unfinished projects. A substantial part of this investment will be lost forever and the remaining will see time and cost overruns rendering the projects unviable.

An example of the state of affairs of the much-touted Pradhan Mantri Gram Sadak Yojana (Prime Minister's Rural Road Program) would be a case in point. The government launched the



Pradhan Mantri Gram Sadak Yojana in December 2000 as a 100% federally sponsored scheme with the objective of providing road connectivity to all unconnected habitations with a population of 1,000 (500 for hilly areas) and above by 2003 and those with a population of 500 and above (250 for hilly areas) by the end of the 10th Development Plan (March 2007). The program was to provide connectivity to 141,000 unconnected habitations and also upgrade the existing roads. An amount of Rs582 billion was estimated to be the funding requirement for the period ending March 2007.

A performance audit carried out by the comptroller and auditor general (CAG) of the program was conducted between January and June 2005 covering the period 2000-05. This included a test check of Rs15.95 billion or 16.92% of the total reported expenditure and also involved technical inspection of 51 roads in four states carried out through the Central Road Research Institute in New Delhi. The audit revealed the following:
  • Though five out of seven years of the life of the program were completed, only 33,875 or 24% of the initially targeted 141,000 habitations (revised to 173,000 in March 2005) were provided with connectivity up to March 2005.
  • The funds utilized between 2000 and 2005 were Rs122.93 billion, which was only about 30% of the proportionate estimated requirement of Rs 415.71 billion up to March 2005, going by the initial estimate of Rs582 billion for seven years.
  • Program funds amounting to Rs3.13 billion or 19.58% of the test-checked expenditure were diverted or parked in unauthorized deposits, or spent on unapproved or inadmissible items of work or used in making undue payments to contractors.
  • Works were executed by the states without conforming to the standard design and specifications prescribed in the Rural Roads Manual. This involved the additional expenditure of Rs1.68 billion.
  • A total of 143 works were abandoned midway or remained incomplete after incurring expenditures of Rs440 million as the land required was not made available by the states. Seven percent or 1,653 completed works took more than the stipulated time of nine months, with delays ranging up to a maximum of 39 months.
  • The test-checking of records in the states showed that an amount of Rs500 million was spent on unapproved items of work executed in 17 states, Rs600 million was charged to the program toward tender premium and lead charges that were not admissible, and undue benefit involving Rs340 million was extended to the contractors. Also, the target date for the execution of works was extended up to 39 months and liquidated damages amounting to Rs350 million were not recovered from the contractors.

    Clearly, as a CAG mentioned, the program was taken up without assessing the magnitude of the work involved and without any realistic assessment of the funds that could be mobilized. The guidelines had to be revised more than once up to November 2004 and the ministry did not have clear targets to monitor the progress and achievements.

    And this is just one of the instances. Things are hardly any different in the case of investments in social infrastructure. For example, Sarva Shiksha Abhiyan or SSA (Education for All) was launched with the aim of enrolling all out-of-school children and establishing education guarantee centers, alternative schools and back-to-school camps by 2003. The date was revised to 2005 only in March of that year. However, out of 34 million children (as on April 1, 2001), 13.6 million or 40% of the children aged six to 14 years remained out of school as of March 2005, four years after the implementation of the scheme and after having incurred an expenditure of Rs111.34 billion.

    Some of the findings of the performance audit are:
  • Funds were irregularly diverted to activities/schemes that were beyond the scope of SSA. In the districts test-checked by audit in 11 states, Rs9.99 million was spent on items not permitted under SSA. Besides, in 14 states/union territories (UTs), financial irregularities of Rs47.25 million were also identified.
  • Five states/UTs failed to maintain the SSA norm of 1:40 for teacher/student ratio. The ratio in primary schools and upper primary schools ranged between 1:60 and 1:130 in test-checked districts of Bihar. Cases of uneven distribution of teachers among schools were identified. Rural schools did not have enough teachers.
  • A total of 75,884 primary schools in 15 states/UTs were operating with only one teacher and 6,647 schools in seven states had no teacher.
  • SSA envisaged the establishment of at least one primary school/education guarantee scheme/alternative innovative education center within 1 kilometer of each habitation throughout the country. The audit revealed that such a facility did not exist in 31,648 habitations in 14 states/UTs.
  • There were delays ranging between one and nine months in supplying free textbooks in seven states/UTs. This could have adversely affected the pass percentage of the students. Free textbooks were not supplied to 750,000 children.
  • A large number of schools in most of the states/UTs were functioning without buildings. Drinking water, toilets or separate toilets for girls, electricity and compound walls were mostly not available. Repairs and maintenance grants were released without specific proposals and also even to schools without their own buildings.
  • In two districts in the state of Jharkhand, school grants of Rs4.79 million were released to 2,369 non-existent schools.

    More than five decades after India's independence and one and a half decades after reforms, the Indian economy has such inadequate infrastructure that the monsoon-dependence of the agricultural sector has almost remained the same. As of now, Rs500 billion worth of agricultural produce in India is wasted because of inadequate infrastructure. It is a criminal waste in a country where about 30% of the population lives in poverty. Every monsoon failure leads to a spate of suicides by Indian farmers who are unable to withstand their worsening debt burden.

    Reforms, anyone?

    Kunal Kumar Kundu is a senior economic analyst with a leading foreign bank in India.

    (Copyright 2006 Asia Times Online Ltd. All rights reserved. Please contact us about sales, syndication and republishing.)
  •  1 2 Back

     

     
     



    All material on this website is copyright and may not be republished in any form without written permission.
    © Copyright 1999 - 2006 Asia Times Online Ltd.
    Head Office: Rm 202, Hau Fook Mansion, No. 8 Hau Fook St., Kowloon, Hong Kong
    Thailand Bureau: 11/13 Petchkasem Road, Hua Hin, Prachuab Kirikhan, Thailand 77110