WRITE for ATol ADVERTISE MEDIA KIT GET ATol BY EMAIL ABOUT ATol CONTACT US
Asia Time Online - Daily News
             
Asia Times Chinese
AT Chinese



    South Asia
     Jul 25, 2009
India-Kashmir rail link lurches forward
By Haroon Mirani

SRINAGAR - What could be Asia's most spectacular railway, or its most dangerous, has made a renewed lurch towards completion thanks to a recommendation that building should resume on the world's highest bridge - a key part of the much-delayed project linking Kashmir and India.

India Railways board chairman M Ravindra and his seven-member expert committee have recommended that work go ahead on the Chenab bridge after the group was asked last December to suggest a possible new alignment in the section following suspension of the work over concerns of safety and stability.

The contentious steel-arch bridge over the river Chenab would run for 1.3 kilometers, with a height of 359 meters, 16 meters higher

 

than the world's present highest vehicular bridge, the cable-stayed Millau Viaduct in France. Almost half of the US$100 million Chenab bridge had been built when construction was halted.

An Indian Institute of Science report warned that the bridge was liable to collapse as the surrounding mountain would have been unable to bear its weight (26,000 tonnes in steel alone).

Ravindra's team accepted there are serious problems in the present alignment and recommended that 93 kilometers of the treacherous 125km link between Katra and Qazigund, out of a total route length of 287km - be abandoned. But he advocated that the large-arched bridge, to be built in an area where winds can blow at 220km per hour, be kept in the plans. Around three billion rupees (US$61 million) had been spent on the bridge before work was stopped.

The line, between Srinagar, summer capital of India-administered Kashmir, and the nearest rail head in Udhampur, nearly 300km to the south, is hailed as one of the most difficult railways lines to be built anywhere, spanning mountainous and often uninhabitable terrain. Most of the line runs either through tunnels (totaling 109km, the longest at 11.4km) or on bridges (783), many spanning deep gorges.

Almost half of the track passes through little-charted areas where there is no habitation, power supply or roads.

Ravindra's recommendation is part of a war between the two powerful lobbies in Indian Railways favoring two separate alignments.

The government suspended work on the line in September 2008 after a report by the Bangalore-based Indian Institute of Science stated that the present alignment of railway line is unsafe. Indian Railways proposed a new alignment it claimed to be more secure.
Satish Kumar Vij, Railway Board Member (Engineering), the top engineering post in Indian Railways, was instrumental in pushing for suspension of the work, citing geological and security reasons. Vij retired on March 31, and a lobby that wants to continue with old alignment gained strength.

Four days before retiring, Vij requested that Delhi Metro Rail Corp chief E Sreedharan intervene in the matter. Sreedharan wrote to the government urging it to immediately cancel the old alignment on the grounds that the line would be unstable and going by the present pace of work it would take 20 years to complete.

Sreedharan, already respected through his running of Delhi Metro Rail Corp, has increasingly become a person others listen to after being among the first to air suspicions of work linked to Satyam Computer Services when he was consultant to the Andhra Pradesh state government for a metro project involving Maytas, a Satyam unit. Weeks later, in January this year, it was disclosed that Satyam had fudged its accounts to the tune of US$1 billion.

The proposed new alignment is based on a steeper gradient of 1-in-60 (a gain of one meter height every 60 meters) compared with the earlier proposed 1-in-100. In a bid to scuttle the change, Vij's successor, Rakesh Chopra, and Shri Prakash, Indian Railways Board (Traffic), then ordered that the gradient should in no circumstances exceed 1:80.

Some engineers say the proposed steeper gradient will make it extremely difficult to run loaded freight trains, while the prospect of longer tunnels has raised questions of access, ventilation and safety. One tunnel in the new alignment would be 26km long.

Meanwhile, one grouping inside Indian Railways argues that the geography in both proposed alignments is same and the existing problems will remain - so the original line should be followed with minor modifications.

Construction is being led by two main companies, Konkan Railway and government-controlled IRCON, involving around 50,000 people. Several foreign companies are involved as sub-contractors, including a joint venture involving India-based AFCONS Infrastructure, Ultra Construction and Engineering Co of South Korea, VSL India Private Ltd, Gammon India and Archirodon construction of South Africa.

Foreign consultants involved include Switzerland-based Amberg Consultancy Firm, and Geo Consult of Austria, Consulting Kortes of Finland, and Leonhardt Andra Und Partner, Germany.

The ambitious link has been under construction since 1994. Work speeded up in 2001 after the project was declared a national priority by New Delhi. The federal government estimated that it would be completed by August 2007 on the eve of India's Independence Day celebrations, but the work is nowhere near completion.

Indian Railways is now considering the alternative route, running through twin-tube tunnels rather than skirting the mountains and cutting the distance by about 55km. Critics say it will push the deadline to 2025 and drive up the project's cost to $10 billion from the present $2.5 billion.

Indian Railways had already invested more than $300 million in work done and contracts awarded when work was stopped. Subsequent claims by contractors following order cancellations, delayed deadlines and other legalities are set to increase losses to $500 million if the old alignment is completely abandoned.

The old alignment had a particularly difficult 140km stretch that snaked through tunnels, across bridges or hugging landslide-prone cliffs. Building about 350km of approach road, necessary before work could start on the actual line, was made possible only through the help of the Indian Air Force, which was called in to drop men and machinery to locations by helicopter. Adding to costs, much heavy machinery had to be imported, as India lacks the necessary technology.

As the project stuttered along, tunnels collapsed and landslides undid hard-won progress. The executing agency, charged with drilling 200 meters of tunnel a month, could get through only 70 meters - hence concerns the project would require a further two decades to complete.

Indian Railways has been criticized for starting the project without surveying the ground properly.

"What they did was they got some satellite maps of terrain, drilled at a couple of places and okeyed the project," said a local geologist pleading anonymity as he is not authorized to talk on the subject. "The region falls under highly earthquake-prone zone V. Its rock structure is all dolomite and limestone, which is fractured and is the main cause of landslides and tunnel collapses." The area is home to three active geological fault lines.

Dithering over the railway alignment is costing more than money. More than 40,000 people across 150 villages were affected by the initial route, as thousands of hectares of rare agricultural land was acquired with compensation of little more than the promise of jobs and a better future thanks to the improved links to the outside world.

"Now there is no land, no job and no train," said one villager Bhoori Ram, who had given his land to Indian Railways.

The bureaucrats have other concerns. "The major problem is who will be responsible for $500 million damages that will be incurred in case a new alignment is considered," said a railway official on the condition of anonymity.

As India struggles to coordinate its mega-buck project, it is not being allowed to forget that China finished a similar high-altitude railway line in adjacent Tibet in the remarkably short period of five years. As the Indian media have pointed out, China started the work on the 1,142km section from Golmud to Lhasa in 2001, just as India ordered faster work on the Kashmir railway. China inaugurated the $3.68 billion track on July 01, 2006.

India's strategists, meanwhile, are dreaming of taking the railway line up to the Tibetan plateau, in the Ladakh area of Indian administered Kashmir, but given the track record in the present Kashmir project, the odds are heavily stacked against such an adventure. The line would cost an estimated $4 billion.

In its favor, the extended line could be strategically important for India, as it would help to supply hundreds of thousands of Indian soldiers posted in the conflict zone of Kashmir bordering Pakistan and China. Their only transport link at present is a single highway that is prone to landslides and is often closed in winter.

Haroon Mirani is a Kashmir-based journalist.

(Copyright 2009 Asia Times Online (Holdings) Ltd. All rights reserved. Please contact us about sales, syndication and republishing.)


Yadav celebrates Indian rail triumph (Feb 19, '09)

India gets on board the Trans-Asian Railway (Mar 21, '07)


1.
Pakistan-US plan falls into place

2. Awash in nonsense

3. Jihadi confession rocks India, Pakistan

4. Last chance saloon in Helmand

5. Who is hitting at Hu?

6. Was Enron right?

7. Karmapa Lama: Tibet's young voice

8. Serial war as a way of life

9. Iran's Guards keep on marching

10. Credit crunch, part two

(24 hpurs to 11:59pm ET, July 22, 2009)

 
 



All material on this website is copyright and may not be republished in any form without written permission.
© Copyright 1999 - 2009 Asia Times Online (Holdings), Ltd.
Head Office: Unit B, 16/F, Li Dong Building, No. 9 Li Yuen Street East, Central, Hong Kong
Thailand Bureau: 11/13 Petchkasem Road, Hua Hin, Prachuab Kirikhan, Thailand 77110